Summary
A $2.17 million contract to clean the digesters at the Hale Avenue wastewater treatment plant, with a $1.69 million budget adjustment. Keeping the plant running smoothly protects sewer service for the whole city.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 30, 2026.
Impact analysis
$2,171,250 contract plus a $1,688,156.50 budget adjustment.
All sewer customers in Escondido benefit from reliable wastewater treatment.
No groups negatively affected
Mentions & discussions (2)
Council Meeting (Closed Session 4:00 PM - Cancelled) — September 30, 2026
A $2.17 million contract to clean the digesters at the Hale Avenue wastewater treatment plant, with a $1.69 million budget adjustment. Keeping the plant running smoothly protects sewer service for the whole city.
Escondido unveils California's first agricultural-only water reuse facility
Escondido unveils California's first agricultural-only water reuse facility Smart Water Magazine
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Escondido
What the council decided, in plain English — one email a week.